Report on the delayed Signalling programme

Audit Id 1488445571774
Título Report on the delayed Signalling programme
Tí tulo en el idioma original

Beretning om forsinkelser af signalprogrammet

Danish

Año 2017
Asunto

Transportation

Tipo

Performance

Tipo de acción

Performed by single SAI

Descripción The report concerns the Ministry of Transport, Building and Housing’s management of the Signalling programme for deployment of new signalling systems on the S-Bane (greater Copenhagen area network) in 2018 and on the main national railway lines in 2021. In October 2016, the ministry established that the Signalling programme was delayed by up to three years – to 2021 and 2023, respectively. The purpose of the study is to determine whether the Ministry of Transport, Building and Housing has assessed the viability of the schedule for implementation of the Signalling programme on an adequate basis.
Autor

Denmark

Materiales

Summary

English

Only chapter one (conclusion and summary) is available in English.
See summary
Contacto
Lisbeth Sørensen
ls@rigsrevisionen.dk
http://uk.rigsrevisionen.dk/publications/2017/92016/
  • <fmt:message key='org.eurosai.action.EmailPage' />
  • <fmt:message key='org.eurosai.action.PdfPage' />
  • <fmt:message key='org.eurosai.action.PrintPage' />

Este sitio está gestionado por EUROSAI - Legal disclaimer